What is the estimate at completion for the activities listed?

Activity A is worth $300, is 100% complete, and actually cost $350. Activity B is worth $100, is 95% complete, and actually cost $85 so far. Activity C is worth $200, is 75% complete, and has cost $175 so far. Total budget is $1500. What is the estimate at completion for the activities listed?
A. $1,704.55 US
B. $0.88
C. $1,685.39 US
D. $185.39 US