Project deliverables that have been completed and checked for correctness through the Control Quality process are known as:

Project deliverables that have been completed and checked for correctness through the Control Quality process are known as:
A. Verified deliverables.
B. Validated deliverables.
C. Acceptance criteria.
D. Activity resource requirements.