Which of the following processes are part of the Project Integration Management Knowledge Area?

Which of the following processes are part of the Project Integration Management Knowledge Area?
A. Develop Project Management Plan, Collect Requirements, Create WBS
B. Develop Project Management Plan, Control Scope, Develop Schedule
C. Develop Project Charter, Define Scope, Estimate Costs
D. Develop Project Charter, Direct and Manage Project Execution, Close Project or Phase