What would be the best action to take first?

The database project is approximately 85% complete. The project has had its challenges. As of the last status report, the project appears to be on track regarding cost, schedule and scope.
Senior management lets you know that the sponsor has some very serious concerns about the project. You don’t understand why, based on the last status report.
What would be the best action to take first?
A. Ignore senior management because the project is in good shape
B. Meet with the sponsor to determine the sponsor?s concerns
C. Tell senior management that the project is in good shape
D. Evaluate the schedule and budget to verify the triple constraint health of the project

How To Pass PMP Exam?

PMI PMP PDF dumps.

High quality PMP pdf and software. VALID exam to help you pass.

Download Printable PDF. VALID exam to help you PASS.

Posted in: PMP

Leave a Reply

Your email address will not be published. Required fields are marked *


The reCAPTCHA verification period has expired. Please reload the page.