How is the schedule variance calculated using the earned value technique? 06/16/2017 – by Mod_GuideK 0 How is the schedule variance calculated using the earned value technique? A. EV less AC B. AC less PV C. EV less PV D. AC less EV SHOW ANSWERSCorrect Answer: C Explanation/Reference: How To Pass PMP Exam? PMI PMP PDF dumps. High quality PMP pdf and software. VALID exam to help you pass. Download Printable PDF. VALID exam to help you PASS.