If a team member, when facing schedule delays and cost overruns, develops several alternatives for completing the project successfully on schedule and within budget and asks questions such as, "Can we do it?," "If we do it what are the consequences?," and "Is it really worth the effort involved?,” he or she is primarily motivated by the___________
A. Contingency Theory
B. Expectancy Theory
C. Reinforcement Theory
D. Equity Theory
Correct Answer: B
Explanation/Reference:
Explanation:
Developed by Victor Vroom, Expectancy Theory asserts that people think seriously about how much effort they should put into a task before doing it. Motivation is linked to an expectation of a favorable outcome. It is based on the concept that people choose behaviors that they believe will lead to desired rewards and outcomes.
How To Pass PMP Exam?
PMI PMP PDF dumps.
High quality PMP pdf and software. VALID exam to help you pass.
|
|
Download Printable PDF. VALID exam to help you PASS.
|
|