Which of the following schedule network analysis techniques is applied when a critical path method calculation has been completed and resources availability is critical?

Which of the following schedule network analysis techniques is applied when a critical path method calculation has been completed and resources availability is critical?
A. Applying calendars
B. Resource leveling
C. Resource planning
D. Resource conflict management