The primary benefit of the Plan Schedule Management process is that it:

The primary benefit of the Plan Schedule Management process is that it:
A. provides guidance to identify time or schedule challenges within the project.
B. tightly links processes to create a seamless project schedule.
C. guides how the project schedule will be managed throughout the project.
D. creates an overview of all activities broken down into manageable subsections.