Your customer wants the project to be completed six months earlier than planned. You believe you can meet this target by overlapping project activities. The approach you plan to use is known as________
A. Critical chain
B. Fast tracking
C. Leveling
D. Crashing
Correct Answer: B
Explanation/Reference:
Explanation:
Fast tracking is a way to accelerate the project schedule.