You are the project manager for a major logistics installation project and must obtain specific services from local sources external to your project. Your subcontracts administrator has told you to prepare a product or service description, which is referenced in a_____________
A. Project statement of work
B. Contract scope statement
C. Request for proposal
D. Contract
Correct Answer: A
Explanation/Reference:
Explanation:
The project statement of work describes in a narrative form the products, services, or results that the project will deliver. It references the product scope description as well as the business need and strategic plan.