Home » PMI » PMP » Working in the systems integration field, you are primarily responsible for coordinating the work of numerous subcontractors. Your current project is coming to an end. You have 15 major subcontractors as well as a variety of other sellers. Now that you are closing contracts (procurements), you shouId_____________
Working in the systems integration field, you are primarily responsible for coordinating the work of numerous subcontractors. Your current project is coming to an end. You have 15 major subcontractors as well as a variety of other sellers. Now that you are closing contracts (procurements), you shouId_____________
A. Conduct a trend analysis
B. Use earned value to assess lessons learned
C. Ask each contractor to meet with you individually at its own expense
D. Conduct a procurement audit
Correct Answer: D
Explanation/Reference:
Explanation:
The procurement audit attempts to identify successes and failures relative to the procurement process especially in terms of the preparation or administration of other procurement contracts on the project or on other projects in the organization. Uncovering and reporting both successes and failures can contribute to the project management knowledge base and improve the quality of project management services. A procurement audit should be conducted as part of the close procurements process.
How To Pass PMP Exam?
PMI PMP PDF dumps.
High quality PMP pdf and software. VALID exam to help you pass.
|
|
Download Printable PDF. VALID exam to help you PASS.
|
|