What is the estimate at completion for the activities listed?

Activity A is worth $200, is 100% complete, and actually cost $200. Activity B is worth $75, is 90% complete, and actually cost $120 so far. Activity C is worth $200, is 75% complete, and has cost $175 so far. The total budget is $1000. What is the estimate at completion for the activities listed?
A. $1100.04
B. $690.63
C. $1186.24
D. $1000