What is the critical chain method?

What is the critical chain method?
A. A technique to calculate the theoretical early start and finish dates and late start and finish dates
B. A schedule network analysis technique that modifies the project schedule to account for limited resources
C. A schedule compression technique that analyzes cost and schedule trade-offs to determine how to obtain the greatest amount of compression for the least incremental cost
D. A technique to estimate project duration when there is a limited amount of detailed information about the project