Which of the following_______

You have been a project manager for seven years. You now are managing the construction of a new facility that must comply with the government’s newly issued environmental standards. You want to ensure that your team members are able to select methods to complete various activities on the project without needing to involve you in each situation. As you prepare your human resource management plan, you should document this information in which of the following_______
A. Roles and responsibilities section
B. Resource assignment matrix
C. Resource breakdown structure
D. Staffing management plan