Which type of estimating?

Using values such as scope, cost, budget, and duration or measures of scale such as size, weight, and complexity from a previous similar project as the basis for estimating the same parameter or measurement for a current project describes which type of estimating?
A. Bottom-up
B. Parametric
C. Analogous
D. Three-point