Home » PMI » PMP » When managing current projects, it is important to use lessons learned from previous projects to improve the organization’s project management process.
When managing current projects, it is important to use lessons learned from previous projects to improve the organization’s project management process.
Therefore, in project closing procedures, it is important to review the_______________
A. Secondary risks that occurred
B. Checklists for identify risks
C. WBS dictionary
D. Fallback plan
Correct Answer: B
Explanation/Reference:
Explanation:
Checklists are a tool and a technique of the identify risks process and include risks encountered on similar, previous projects identified through the lessons learned process and from other sources. The project team should review the checklist as part of the identify risks process as well as during closeout. The team should add to the list as necessary, based on its experience, to help others in the future.
How To Pass PMP Exam?
PMI PMP PDF dumps.
High quality PMP pdf and software. VALID exam to help you pass.
|
|
Download Printable PDF. VALID exam to help you PASS.
|
|