A customer has stated that meeting the project schedule and milestones takes priority and is, therefore, willing to spend additional funds to sustain operations.

A customer has stated that meeting the project schedule and milestones takes priority and is, therefore, willing to spend additional funds to sustain operations.
The project team must ensure completion of the:
A. business continuity plan.
B. incident response plan.
C. disaster recovery plan.
D. risk management plan.
E. quality management plan

comptia-exams

Leave a Reply

Your email address will not be published. Required fields are marked *


The reCAPTCHA verification period has expired. Please reload the page.