Which of the following roles has the responsibility of resolving the issue?

One of the tasks on a project’s critical path is progressing too slowly. The team member who is responsible for completing the task is assigned to multiple projects with aggressive deadlines.
Which of the following roles has the responsibility of resolving the issue?
A. CCB
B. PMO
C. Project sponsor
D. Project scheduler