Which of the following is described as placing responsibility for addressing the potential effects of an uncertain future event on an entity outside the organization?

Which of the following is described as placing responsibility for addressing the potential effects of an uncertain future event on an entity outside the organization?
A. Risk avoidance:e
B. Risk transfer
C. Risk exploitation
D. Risk mitigation