Which of the following can be determined?

An active project has a CPI of 0.92. Which of the following can be determined?
A. The project is currently over budget.
B. The project has a budget surplus.
C. The project is ahead of schedule.
D. The project is behind schedule.

comptia-exams

3 thoughts on “Which of the following can be determined?

  1. If the ratio has a value higher than 1 then it indicates the project is performing well against the budget. A CPI of 1 means that the project is performing on budget. A CPI of less than 1 means that the project is over budget.

    It’s A