Which of the following is MOST likely to be the first document created by the project manager?

A vendor has accepted a proposed project from a customer.
Which of the following is MOST likely to be the first document created by the project manager?
A. Project charter
B. Project management plan
C. Project statement of work
D. Project schedule

comptia-exams

0 thoughts on “Which of the following is MOST likely to be the first document created by the project manager?

  1. C is wrong. The correct answer is B, because an SOW is done before the bidding process. It is done before the vendor accepts the project. “Vendors use the SOW to determine whether they
    are capable of producing the deliverables and to determine their interest in bidding on
    your project work.”