A project manager has contracted a third-party vendor to achieve milestones. Which of the following risk strategies is the project manager applying?
A. Transfer
B. Accept
C. Avoid
D. Mitigate
A project manager has contracted a third-party vendor to achieve milestones. Which of the following risk strategies is the project manager applying?
A. Transfer
B. Accept
C. Avoid
D. Mitigate