Which of the following tools should the project team select to determine the possible origins of the increased costs?

A team has been assembled and assigned a project to reduce recent, unanticipated production cost overruns. Which of the following tools should the project team select to determine the possible origins of the increased costs?
A. Pareto chart
B. Fishbone diagram
C. Process diagram
D. Run chart

comptia-exams

Leave a Reply

Your email address will not be published. Required fields are marked *


The reCAPTCHA verification period has expired. Please reload the page.