In a project with a BAC of $235,000, the CPI is 0.80, and the SPI is 1.20. Based on this information, which of the following can the key stakeholders determine about the project?
A. The project is under budget and ahead of schedule.
B. The project is over budget and ahead of schedule.
C. The project is under budget and behind schedule.
D. The project is over budget and behind schedule.
B is correct
CPI1.0, the task is under budget
SPI1.0, the task is ahead of schedule
I agree….I think the correct answer should be B.
B is correct.
CPI is 0.80: project is over budget
SPI is 1.20: ahead of schedule
so B is correct answer.