A project is coming to the end of a phase. The PMO required that the quality team review the work and budget before moving on to the next phase of the project.

A project is coming to the end of a phase. The PMO required that the quality team review the work and budget before moving on to the next phase of the project.
The project manager must schedule the review of the phase and have the stakeholders present. This review is referred to as:
A. change management.
B. a milestone.
C. a tollgate.
D. an incident response.

comptia-exams

3 thoughts on “A project is coming to the end of a phase. The PMO required that the quality team review the work and budget before moving on to the next phase of the project.

  1. This is a tollgate C.

    A Tollgate Review, as the name indicates, is like a checkpoint in a Six Sigma project at which the various team members meet and determine whether the work has been performed as indicated in the project plan and whether the objectives mentioned have been achieved.

    1. On the other hand, COMPTIA study guide says:
      A milestone is a control point event in a project with zero duration that triggers a reporting requirement or requires sponsor or customer approval before proceeding with the project.
      So, milestone definition also checks out.