A new corporate policy was approved that will positively affect the project.
Which of the following should the project manager do FIRST?
A. Schedule the change
B. Review the communication plan
C. Update the issue log
D. Update the risk register
A new corporate policy was approved that will positively affect the project.
Which of the following should the project manager do FIRST?
A. Schedule the change
B. Review the communication plan
C. Update the issue log
D. Update the risk register
how does the communication plan have anything to do with a positive policy ? its D update the risk register. If you are positively affecting the project the risk will reduce ? this question is terrible