The project team is moving from high-level risks to detailed risks. Which of the following project phases is the project team moving between?
A. Execution to monitor and control
B. Initiation to planning
C. Initiation to monitor and control
D. Planning to execution

comptia-exams

2 thoughts on “Which of the following project phases is the project team moving between?

  1. B is the correct answer. In the CompTIA Project+ Objective is clearly shows in 1.3 Compare and contrast standard project phases. Under Initiation – high level risk > Under Planning – detailed risks thus Initiation to planning.