Which of the following should be tasked with ensuring resources are appropriately allocated to projects?

An organization has multiple projects that are taking place simultaneously.
Which of the following should be tasked with ensuring resources are appropriately allocated to projects?
A. PMO
B. Project sponsor
C. Project coordinator
D. HR

comptia-exams

One thought on “Which of the following should be tasked with ensuring resources are appropriately allocated to projects?

  1. B is a wrong answer.
    On page 5, the study guide says:
    Some of the primary functions of the PMO include: Managing shared resources across projects managed by the PMO.
    Also, on page 7, it says about PMO:
    It focuses on providing: Support for resource allocation.
    Correct answer is:
    A. PMO