Which of the following should the project manager consider as a root cause for potential issues with cost overruns?

Gas prices were included in the cost baseline for a transportation and hauling project. Although the estimates used to create the baseline were based on historical data, which of the following should the project manager consider as a root cause for potential issues with cost overruns?
A. Requirements
B. Lessons learned
C. Budget
D. Environment

comptia-exams

One thought on “Which of the following should the project manager consider as a root cause for potential issues with cost overruns?

  1. The “root cause” is the environment…. since it’s totally out of the control of the project

Leave a Reply

Your email address will not be published. Required fields are marked *


The reCAPTCHA verification period has expired. Please reload the page.