Gas prices were included in the cost baseline for a transportation and hauling project. Although the estimates used to create the baseline were based on historical data, which of the following should the project manager consider as a root cause for potential issues with cost overruns?
A. Requirements
B. Lessons learned
C. Budget
D. Environment
The “root cause” is the environment…. since it’s totally out of the control of the project