Which of the following risk strategies should the project manager adopt?

A project manager has an opportunity to add a highly skilled expert to the team who can increase the probability of the project’s success. Which of the following risk strategies should the project manager adopt?
A. Exploitation
B. Avoidance
C. Acceptance
D. Mitigation