A project manager is reviewing documents to develop the project charter. While reviewing historical project documentation, the project manager decides to include the following in the charter:
Project title description Preassigned resources
Budget
WBS Measurable project objectives
Which of the following components should be a part of the project management plan instead of the project charter?
A. Project title and description
B. Preassigned resources
C. Budget
D. WBS
E. Measurable project objectives

comptia-exams

One thought on “Which of the following components should be a part of the project management plan instead of the project charter?

  1. Another horribly worded question. Everything until the last sentence is a distractor. However, from the 2nd edition study guide:
    “The key components of the project management plan include the following documents:
    Scope statement, Project schedule, Communication plan, Resource plan, Procurement plan, Project budget, Quality management plan, Risk management plan”.
    So given all that, the most correct answer from the guide is C, budget.

  2. Work Breakdown Structure (WBS) is a hierarchical decomposition of the total scope of work to be carried out by the project team to accomplish the project objectives and create the required deliverables.

    1