Which of the following documents would contain these items?

During the initiation phase, a project manager has asked for a document containing the high-level objectives and goals for a project. Which of the following documents would contain these items?
A. Business case
B. Requirements document
C. Project timeline
D. Task plan

comptia-exams

3 thoughts on “Which of the following documents would contain these items?

  1. References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, Page 138 talks about the “Requirements Document.” It is done during the planning phase, not in the initiation phase. Also, it contains details of the objectives and goals, not high-level objectives and goals. High-level objectives and goals are in the Project Charter and Business Case, both of which are within the Initiation phase.
    Therefore the correct answer is A

  2. Requirements Documentation is not the same as “Requirements Document” – None of my studies suggests a document called “requirements document” but they do list “Business Case.” Requirements Documents is a general grouping of all required documents – there is no specific document with this name from my reading. I think the correct answer is A.

    1. References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, Page 138 talks about the “Requirements Document.”

  3. Requirements Documentation. Projects cannot be implemented without the proper requirements. Requirements documentation in project management describes how each requirement meets the business needs for the project. … It captures the project requirements and ensures that they meet the expectations of the stakeholders.

    Answer is B