A project manager would like to bring vendors into a new project. Which of the following documents should the potential vendors submit so the project manager can find the best vendors for the project?
A. SLA
B. SOW
C. Change request
D. RFP
A project manager would like to bring vendors into a new project. Which of the following documents should the potential vendors submit so the project manager can find the best vendors for the project?
A. SLA
B. SOW
C. Change request
D. RFP
B is wrong, the correct answer is D. The SOW us submitted by the PM so that the prospective vendors can use it…
“Vendors use the SOW to determine whether they
are capable of producing the deliverables and to determine their interest in bidding on
your project work.”