Which of the following is the critical path if one day is added to each task for quality control?

During a project, the project manager discovers there is insufficient time allotted for quality control. The project manager prepared to submit a revised schedule to the CCB.

Given the attached chart, which of the following is the critical path if one day is added to each task for quality control?
A. 12 days
B. 16 days
C. 17 days
D. 22 days

comptia-exams

2 thoughts on “Which of the following is the critical path if one day is added to each task for quality control?

  1. Correct answer is:
    (Task 1 +1 day) + (Task 3 + 1 day) + (Task 4 + 1 day) + lag + (Task 5 + 1 day) =
    2 + 4 + 7 + 2 + 3 = 18 days.