Which of the following types of reports should the project sponsor use to quickly summarize the status report data?

Upper management asks a project sponsor to provide several ad hoc reports as a brief overview of the project’s current status.
Which of the following types of reports should the project sponsor use to quickly summarize the status report data?
A. Pie chart
B. Run chart
C. Project schedule
D. Dashboard information