Which of the following is the BEST way for the PM to validate the assessment?

New requirements were introduced during the execution phase of a project, and the team believes this will impact the project cost but not the timely completion of project deliverables.
Which of the following is the BEST way for the PM to validate the assessment?
A. Ask the team for estimates, and review the project schedule and budget.
B. Ask the team to review the product scope and validate its impact on the schedule and quality.
C. Ask the team for estimates, and review the cost management plan.
D. Ask the team to perform a SWOT analysis, and validate the assessment.

comptia-exams

2 thoughts on “Which of the following is the BEST way for the PM to validate the assessment?

  1. D is definitely a wrong answer.
    The team does not perform SWOT analysis, the PM does, with the help of the team (or SMEs etc.).
    The team must provide estimates to the PM.

    1
    1
  2. Strengths, Weaknesses, Opportunities, and Threats (SWOT) Another technique you can use to identify risks is called SWOT analysis. This involves analyzing the project from each of these perspectives: strengths, weaknesses, opportunities, and threats. It also requires examining other elements such as the project management processes, resources, the organization, and so on.

Leave a Reply