When the project sponsor announced that the project needed to stop because of shifting strategic priorities.

A project team started work on a project and was ahead of schedule when the project sponsor announced that the project needed to stop because of shifting strategic priorities.
The constraint described in this scenario is:
A. cost
B. environmental
C. scope
D. scheduling