Which of the following documents should the project team reference to fast-track the project?

A program manager informs a project manager that a new, high-priority project has been approved and will need the current project’s resources before the scheduled project close date. The project team meets and determines that the project should be fast-tracked.
Which of the following documents should the project team reference to fast-track the project? (Choose two.)
A. Scope management plan
B. Configuration management plan
C. Network diagram
D. Project schedule
E. Project plan