Which of the following are NOST likely missing from the project?

A project team is not delivering their tasks in a timely manner. Additionally, tasks are being reworked because requirements continue to be identified as work packages are being delivered.
Which of the following are NOST likely missing from the project? (Select two.)
A. Project charter
B. Organizational chart
C. Scope document
D. Status report
E. Business case
F. Project plan

comptia-exams

One thought on “Which of the following are NOST likely missing from the project?

  1. The business case documents the reasons for the project, justification for the project, and how it fits in with the company objectives. It establishes the justification for the project, how it aligns to the strategic goals of an organization, and the business need or opportunity that brought about the project.

    As the project manager, it’s your responsibility to write the project plan and make certain everyone, including team members and key stakeholders, understands that plan. The project coordinator will assist you in preparing the plan, in cross-functional coordination with the business areas that will participate on the project, and with preparing time and resource schedules.

    The first planning topic discussed is the project scope document.

    Project scope includes all the components that make up the product or service of the project and the results the project intends to produce.
    Scope planning will assist you in understanding what’s included in the project boundaries and what is excluded.