A project has passed a phase-gate, and the new phase is ready to begin. Which of the following is the MOST appropriate method to communicate the transition to team?
A. Kickoff meeting
B. One-on-one meetings
C. Voice conferencing
D. Instant messaging
Why not C
A
Keep in mind that kickoff meetings are either between either the Initiating and Planning Phase or between the Planning and Execution phase. The question does not describe phase. Since a phase can be less significant than the phases just mentioned the answer could easily be B.