Which of the following network scheduling techniques is focused mainly on the duration and stack of each activity?

Which of the following network scheduling techniques is focused mainly on the duration and stack of each activity?
A. Program evaluation review technique
B. Precedence diagramming method
C. Arrow diagramming method
D. Critical path method

comptia-exams

One thought on “Which of the following network scheduling techniques is focused mainly on the duration and stack of each activity?

  1. Critical Path is NOT a “scheduling technique”… it is the evaluation of a schedule that has already been completed