A project team completed a brainstorming activity to determine potential issues with a project. Which of the following activities should the project team do NEXT?
A. Risk identification
B. Risk quantification
C. Risk planning
D. Risk response
A project team completed a brainstorming activity to determine potential issues with a project. Which of the following activities should the project team do NEXT?
A. Risk identification
B. Risk quantification
C. Risk planning
D. Risk response
Why not B? Isn’t the activity of determining potential issues with the project called “risk identification”?