A company has hired a new project manager. The PMO has briefed the new project manager on the following expected responsibilities for projects:
• Coordinate project schedule
• Manage to the triple constraint
• Provide performance feedback to team members’ managers
Which of the following types of organizational structures did the new project manager MOST likely join?
A. Balanced matrix
B. Strong matrix
C. Functional
D. Projectized
The fact the PM provides performance feedback to team members’ managers, is a good indicator it is NOT Projectized
D. Projectized is a WRONG answer.
The fact that there are team manager besides PMs means that the structure is NOT projectized.