Which of the following should the team consult to determine which actions to take?

A change is being implemented on a project, and while in testing, it becomes clear that the change cannot be finalized due to the severe impact it would have on other critical systems. Which of the following should the team consult to determine which actions to take?
A. Incident response plan
B. Regression plan
C. Progress plan
D. Business continuity plan

comptia-exams

2 thoughts on “Which of the following should the team consult to determine which actions to take?

  1. Change requests should also list what the plan is in the event the Change breaks something or causes an issue. This is called the regression plan. This knowledge is from over 15yrs working on contracts.