A new stakeholder has requested the status and progress reports for the project milestones. Which of the following documents should the project manager address FIRST?
A. Project communication plan
B. Project status report
C. Project management plan
D. Project backlog
Answer is B:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 328