Which of the following steps of the control was missed?

A stakeholders asked for a change to the project. The project manager discussed and documented the desired change, and the proper authorities approved it.
Which of the following steps of the control was missed?
A. Communicate the change
B. Quality check
C. Implementation
D. Evaluate impact and justification

comptia-exams

One thought on “Which of the following steps of the control was missed?

  1. There are several aspects to an effective change management system. You’ll look at each of these elements throughout this section. The change management process includes the following:

    Identify and document the change request.
    Track requests in the change request log.
    Evaluate the impact and justification of the change.
    Disposition the request at the change control board (CCB) and approve or deny.
    Implement the change.
    Validate the change and perform a quality check.
    Update the project management plan, update the appropriate project documents, and apply version control.
    Coordinate and communicate with the appropriate stakeholders.

Leave a Reply

Your email address will not be published. Required fields are marked *


The reCAPTCHA verification period has expired. Please reload the page.