Which of the following activities should the project team do NEXT?

A project team completed a brainstorming activity to determine potential issues with a project. Which of the following activities should the project team do NEXT?
A. Risk identification
B. Risk quantification
C. Risk planning
D. Risk response

comptia-exams

One thought on “Which of the following activities should the project team do NEXT?

  1. Risk identification is the process of listing potential project risks and their characteristics. The results of risk identification are normally documented in a risk register, which includes a list of identified risks along with their sources, potential risk responses, and risk categories.