Which of the following should the project manager do?

A project manager has taken over a project that is already in progress. The project manager notices the functional manager of one team is unaware of the current progress. Which of the following should the project manager do? (Choose two.)
A. Update the project charter to include the functional manager as a key stakeholder
B. Publish the project schedule to the functional manager
C. Review the communications plan to ensure proper involvement
D. Add the incident to the issue log and seek resolution
E. Ensure the functional manager is on the status report distribution list

comptia-exams

One thought on “Which of the following should the project manager do?

  1. There’s nothing in the question that leads me to believe that the functional manager should be made stakeholder. So, if awareness is the problem, then the solution is C and E