Which of the following are applicable areas that the review should cover?

A post implementation review is being performed as a part of project closure. Which of the following are applicable areas that the review should cover? (Choose two.)
A. Lessons learned during the project.
B. Produce operational support documentation.
C. Gathering and centralizing project documentation.
D. Organizing the communication of project closure.
E. Identify the key project achievements.
F. Provide a recap of the overall solution.

comptia-exams

Leave a Reply

Your email address will not be published. Required fields are marked *


The reCAPTCHA verification period has expired. Please reload the page.