A non-stakeholder approaches the project manager and asks if certain items can be added to a project that was started two months earlier. Which of the following constraints does this impact MOST?
A. Time
B. Schedule
C. Scope
D. Cost
A non-stakeholder approaches the project manager and asks if certain items can be added to a project that was started two months earlier. Which of the following constraints does this impact MOST?
A. Time
B. Schedule
C. Scope
D. Cost
In reply to Anonymous, requests can also be for changes that are IN scope.
Why not C?
I think new items mean new requirements which then change the scope.